Event Center needs $300K in repairs. Middletown Council concerned about cost

Central Connections held a ribbon cutting and tour of their renovated facility Tuesday, Nov. 1, 2022 on Central Ave. in Middletown. The $900,000 in renovations have turned the senior center into a recreation center with full restaurant and bar, bridal suite and rooms to host weddings, fitness room and more. NICK GRAHAM/STAFF

Credit: Nick Graham

Credit: Nick Graham

Central Connections held a ribbon cutting and tour of their renovated facility Tuesday, Nov. 1, 2022 on Central Ave. in Middletown. The $900,000 in renovations have turned the senior center into a recreation center with full restaurant and bar, bridal suite and rooms to host weddings, fitness room and more. NICK GRAHAM/STAFF

Middletown City Council on Tuesday tabled approving money for heating and cool repairs at the Event Center of Middletown after eyeing the unexpected price tag of more than $300,000.

The center on Central Avenue that also houses senior citizens activities was purchased by the city in 2023 for $1.8 million with American Rescue Plan Act (ARPA) funds from the Middletown Area Senior Citizens Inc. following financial difficulty of Central Connections and the termination of the former director for alleged theft.

The center has been reborn with daily senior activities and is booking special occasion events to fund further senior activities.

But keeping large building at a uniformly comfortable temperature has been a challenge for the city maintenance staff, according to Acting City Manager Nathan Cahall.

When the city took it over some wondered about portable air conditioning units in some areas of the building.

The problem is the air handlers that push the heat/cool air through the duct work, according to maintenance workers.

The Event Center’s current air handlers for the HVAC system are undersized for the building. The current equipment is approximately half the size of the original system that was installed when the building was constructed. As a result, the system is unable to properly cool and heat the building, which leads to costly maintenance and repair costs, according to a city staff report.

Council members indicated they want to look at alternatives before approving an expenditure of $318,890 from the city’s property development fund.

“I have reservations about putting this amount of money in to that project at this time,” said Councilman Paul Lolli. He noted there decisions that have to be made soon about downtown properties the city owns including the Manchester Inn, which is vacant.

Councilman Paul Horn, an electrician, said he is “shocked” that the commercial building was built without the proper air handler size.

Cahall said he shares Horn’s shock. The staff determined the air handlers currently in place were installed in 2015.

“Someone saved some money and now we are being punished for it,” Horn said.

Council asked staff to explore getting a mechanical engineer to review the situation with a recommendation for possible alternatives.

Another concern is the time it will take to purchase the machinery to repair the issue, which is estimated to be 14 weeks. Cahall said the center is beginning to see bookings for events into summer 2025.

“The problem we are running in to is equalizing temperature and humidity in the building,” Cahall said. But the staff is in the process of finding a firm to do a comprehensive assessment to “either confirm or deny things or maybe come up with some alternatives.